220kV桂竹至海丰送电线路工程
质量保证大纲
批准: 程 文 辉
审核: 符 永 江
编写: 杜 钢
广东省输变电工程公司 220kV桂海线路工程项目部
2002年9月
目 录
1、范围 ···························································································· 1 2、引用文件 ····················································································· 1 3、工程概况 ····················································································· 1 4、质量保证大纲的内容和要求 ························································· 2 5、本质量保证大纲的管理 ······························································ 13 附录一 ···························································································· 15 附录二 ···························································································· 16 附录三 ···························································································· 17
1、范围
本质量保证大纲规定了220kV桂竹至海丰送电线路工程质量保证的内容和要求。目的是防止工程从开工到竣工投产的所有阶段中出现不合格,以使工程质量达到合同和有关规定的要求,并令顾客满意。
本质量保证大纲适用于220kV桂竹至海丰送电线路工程施工,并向顾客提供证实工程的过程控制能力。
2、引用文件
QB/GDTC-QAS-1999 QB/GDTC-QSFd9-1-1999
QB/GDTC-QSP15-1999
质量保证手册 工程项目技术管理制度
搬运、贮存、包装、防护和交付程序
3、工程概况
220kV桂竹至海丰送电线路工程,由220kV桂竹变电站220kV出线构架起,至220kV海丰变电站的220kV进线构架止,其中水泥杆21基,铁塔36基,共57基,全长21.34千米。其中单回路为17.79千米,双回路为3.55千米(双回路部分本期工程仅架一回导线和2根地线)。导线采用2×LGJX-300/40型钢芯稀土铝绞线,每相导线为双分裂,子导线分裂间距形式为垂直排列,分裂间距为0.4米,右地