管沟土方施工方案 下载本文

内容发布更新时间 : 2024/5/18 10:09:34星期一 下面是文章的全部内容请认真阅读。

元坝气田17亿立方米/年滚动建产地面集输

工程YB27-1/2~YB29复线管道工程

YB204-1~YB205段

桩号BC17-BC35土建施工

施工方案

编制人: 审核人: 批准人: 四川德阳庆达实业有限公司 2016年05月16日

目录

第一章、概述

1、工程概况··························································4 2、编制依据及规范····················································4 3、施工内容及现场情况················································5 第二章、施工准备

1、技术准备··························································8 2、施工队伍准备······················································8 3、物资准备(机械、材料、资金)·······································11 4、建立项目HSE管理制度··············································11 5、现场施工条件准备··················································12 第三章、施工方案

1、测量······························································13 2、土石方开挖························································14 3、土石方回填························································18 4、水工保护··························································22 第四章、各项管理和保证措施

1、管理目标保证措施·················································28 2、工程质量保证措···················································28 3、安全技术保证措施·························29 4、文明施工保证措施·························29 5、工期保证措施···························30 第五章 施工进度计划·················································32 第六章工作危害分析表················································33 第七章 应急预案

1、应急预案·························································37 2、编制依据·························································38 3、组织管理职责·····················································39 4、应急程序·························································41 5、事故危险状态识别·················································44

2

6、应急预案报告程序·················································45 7、应急指令及应急指挥···············································46 8、疏散程序·························································48 9、救护方案·························································48 10、管道破坏预案····················································49 11、沟槽塔方预案····················································49 12、泄露预案························································49 13、恢复常态工作····················································50

3

第一章 概述

第一节 工程概况

1、工程概况:

1.1、本工程概况:本工程为元坝气田17亿立方米/年滚动建产地面集输工程YB27-1/2~YB29复线工程,天然气管道管沟土石方开挖及回填工程。 1.2、工程名称:站外部分集输管网YB204-1~B205 土建施工

1.3、工程起止范围:YB204-1~YB205.起点里程为2km+258.3m,桩号BC17;终点里程为4km+254.4m,桩号BC35、实际长度约为2.833公里 2、编制依据及施工规范

根据元坝气田17亿立方米/年滚动建产地面集输工程YB27-1/2~YB29复线工程施工蓝图。和现场踏勘实际情况及国家现行的法律、法规,地区颁发的安全、消防、环保等管理规定。 2.1、编制依据

《中华人民共和国安全生产法》(2014修订)

《建设工程安全生产管理条例》国务院第393号(2004) 《中华人民共和国节约能源法》主席令第90号(1997)

《中华人民共和国环境保护法》(主席令第九号)【2015-01-01实施】 《中华人民共和国水土保持法》主席令第38号(2010) 《中华人民共和国防洪法》(1997年)

《中华人民共和国野生动物保护法》(主席令第24号)(2009年修正本) 《中华人民共和国土地管理法》(1998年8月29日) 《中华人民共和国消防法》(1998年5月1日实施) 《建设项目环境保护管理条例》国务院令第253号(1998)

《中华人民共和国石油天然气管道保护法》主席令(第三十号)(2010) 《建设工程安全生产条例》国务院令393号(2003) 2.2、施工质量规范

中石化江汉油建工程有限公司质量手册 Q/JHJ G3001-2012 中石化江汉油建工程公司质量控制程序 Q/JHJ GQP-2012

中石化江汉油建工程有限公司项目质量计划编制导则 Q/JHJ2128-2012

4

国家现行的有关规定、规范

给水排水构筑物工程施工及验收规范 GB50141-2008 土方与爆破工程施工及验收规范 GB50201-2012

建筑地基基础工程施工质量验收规范 GB50202-2002(2011版) 砌体工程施工质量验收规范 GB50203-2011

混凝土结构工程施工质量验收规范 GB50204-2002(2011版) 钢结构工程施工质量验收规范 GB50205-2011 屋面工程质量验收规范 GB50207-2012 地下防水工程质量验收规范 GB50208-2011 建筑地面工程施工质量验收规范 GB50209-2010 建筑装饰装修工程质量验收规范 GB50210-2011 给水排水管道工程施工及验收规范 GB50268-2008 建筑工程施工质量验收统一标准 GB50300-2013 建筑基坑工程检测技术规范 GB50497-2009 建筑地基处理技术规范 JGJ79-2012 埋地钢质管道阴极保护参数测量方法 GB/T21246-2007 埋地钢质管道阴极保护技术规范 GB/T21448-2008 2.3、安全规范

石油化工建设工程施工安全技术规范 GB50484-2008 施工现场临时用电安全技术规范 JGJ46-2005 建筑施工土石方工程安全技术规范 JGJ 180-2009

3、施工内容及现场情况

本段管道与已建成营运的输气管道近距离并行,施工前须查明该管道的位置、埋深及走向,施工过程中严格控制作业带宽度,严禁采用爆破方式施工。

3.1、BC31~BC35桩管道斜坡向上敷设后,紧靠井场水泥公路敷设,本段管道2次穿越宽约2.0~3.0m的乡村土路,2次穿越宽约3.5~4.0m的村级水泥公路,车流量较小,可采用开挖方式通过,管顶距路面深度不宜小于2.5m,穿越水泥公路建议采取套管保护措施

3.2、BC26~BC30桩管道穿越一小型河流后沿阶梯状斜坡向上敷设,斜坡被各级平台

5