Supplier/Mfg Location:供应商名称及地址: Duns Number: 邓白氏号: Supplier Contact: 供应商联系人: GM SQE: Part Number(s): 零件号: Program(s): 项目: Part Name: 零件名: *Type Key:

S = Design-Supplier 设计- 供应商 T = Tooling 工装

类型描述 G = Design-GM 设计- GM C = Capacity 产能 F = Facilities 设施 L = Late Release 发放滞后 Issue No. Issue Date Severity ssuesDescription and/or Sketch 序号 发布日期 严重度 问题描述 M = Manufacturing/Process 制造/工艺 R = Production Control 生产控制 O = Other 其它

P = Purchasing 采购 Person Forecast Type Responsible Action Plan & Progress to Plan Completion 类型 (Name) Date 措施及现状 责任人 预计完成日期 * Status 状态 Status 状态: 25% Issue Identified 问题已被识别 50% Action Plan Proposed 方案措施 75% Action Plan Implemented 已采取长期措施

100% Issue Resolved 问题已解决

Severity: 1 - Director Support 需要总监支持

严重度 2 - Manager/Supervisor Support 需要经理/主管支持

3 - SQE Support 需要SQE支持

APQP Open Issues.DOC

October 2002

GM1927-5

Reviewed by 审核 __________________(供应商项目经理) Date 日期 __________ Approval by 批准 __________________(项目主管副总经理) Date 日期 __________