PMBOK指南(第5版)第二章习题要点 下载本文

内容发布更新时间 : 2024/12/23 4:11:34星期一 下面是文章的全部内容请认真阅读。

1.You have been assigned as project manager on what could be a \company\around on a sedan chair, if it fails, you will be in the unemployment line. You realize that to be successful you need to exercise maximum control over project resources. Which form of project organization should you establish for this project?

A. Strong matrix B. Projectized

C. Project coordinator D. Weak matrix

1. 你负责管理的一个项目, 这个项目对你来说是成败在此一举。 如果项目成功, 那么你的前途无量;如果项目失败, 那么你就要被炒鱿鱼。 你意识到: 为了使项目成功,你必须对项目资源具有最大程度的控制。 那么你预备建立哪一种项目组织形式来达到你的目的 A. 强矩阵 B. 项目型 C. 项目协调人 D. 弱矩阵

2.Your project is managed under a projectized organization. It has just entered closure. Under the circumstances, which of the following should be your GREATEST concern?

A. Setting yourself up to take over a large multi-year project B. The team is not focused on completing the project. C. You will have extra pressure from the customer.

D. Making sure your manager knows the project is almost completed

2. 你的项目在项目型组织中执行,现在刚进入收尾阶段,在这种情形下你最应该关注的是: A.让自己能接受一个大的多年度的项目 B.这个团队重心不在完成这个项目上 C.你会受到来自客户的额外压力

D.确定你的经理知道这个项目已几乎完成

3. You have been assigned to a project in which the objectives are to direct customer calls to an Interactive Voice Response system before being connected to a live agent. You are in charge of the media communications for this project. You report to the project manager in charge of this project and the VP of marketing, who share responsibility for this project. Which organizational

structure do you work in? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization

3. 你参与一个项目,该项目目标是在客户的电话在未被连接到代理之前,将其接到一个交互式的语音回应系统。你主要负责该项目的信息沟通.你需要向该项目的项目经理和市场VP(与项目经理共同分享项目的权限和职责)汇报工作。你所工作的机构属于下列哪种组织形式? A. 职能组织 B. 弱矩阵组织 C. 项目化组织 D. 平衡矩阵组织

4. What is not true of project life cycle phases? A. They are generally sequential B. They cannot overlap

C. They define what deliverables are produced D. They involve handoffs to other phases 4. 关于项目生命期各阶段的描述哪个是不正确的? A. 它们通常是顺序的 B. 它们不能够重叠

C. 它们定义了将产生何种可交付成果 D. 它们涉及从某个阶段到另一个阶段的交接

5. The major difference between the project coordinator and project expeditor forms of organization is that

A. Strong commitment to the project usually does not exist in the project expeditor form of organization

B. The project coordinator cannot personally make or enforce decisions C. The project expeditor acts only as an intermediary between management and the project team

D. The project coordinator reports to a higher-level manager in the organization 5. 项目协调者类型和项目促进者类型的组织形式之间主要区别在于:

A. 在项目促进者类型的组织形式中,员工们通常对项目没有比较稳固的承诺 B. 项目协调者通常不能以个人名义做出或执行项目决策

C. 项目促进者只是作为管理层和项目团队之间的媒介存在 D. 项目协调者负责向组织中更高层的经理人员进行报告

6. Project A is being administered using a matrix form of organization. The project manager reports to a senior vice president who provides visible support to the project. In this scenario, which of the following statements best describes the relative power of the project manager?

A. The project manager will probably not be challenged by project stakeholders. B. In this strong matrix, the balance of power is shifted to the functional line managers.

C. In this tight matrix, the balance of power is shifted to the project manager. D. In this strong matrix, the balance of power is shifted to the project manager. 6. A项目通过一个组织矩阵进行管理。 项目经理向一位高级副总裁汇报工作, 后者对项目提供实际的帮助。在这种情况下, 以下哪个陈述最好地说明了项目经理的相对权力? A. 项目经理很可能不会受到项目干系人的责难 B. 在这个强矩阵中, 权力的平衡倾向于职能经理 C. 在这个紧密矩阵中, 权力平衡倾向于项目经理 D. 在这个强矩阵中, 权力平衡倾向于项目经理

7. At what point in the project would stakeholders have the most ability to influence the final outputs of the project product? A. Implementation B. Development C. Concept D. Close out

7. 在项目的什么阶段,干系人对项目的最终产品影响能力最强? A. 执行 B. 开发 C. 概念 D. 收尾

8. An organization is going through an evolution phase of restructuring the way it does projects. In a shift from a weak matrix organization to a strong matrix organization, the power is shifted from: A. Project manager to functional manager. B. Expeditor to coordinator.