1马来西亚沐若水电站无水调试方案-最终版 -中文版 下载本文

内容发布更新时间 : 2024/6/3 16:33:10星期一 下面是文章的全部内容请认真阅读。

马来西亚沐若(含生态电站无水调试 方案 (最终稿 2014-Feb. R.3 目录Catalog

1概述GENERAL INTRODUCTION (1 1.1引言F OREWORD (1

1.2电站结构简介I NTRODUCTION OF S TATION S TRUCTURE (1 1.3水轮机基本参数B ASIC P ARAMETERS OF T URBINE (1

1.4主要技术数据B ASIC P ARAMETERS OF H YDRO G ENERATOR (1 1.5调试试验的目的P URPOSE (2

20.415KV厂用电系统无水调试DRY COMMISSIONING OF 0.415KV STATION SERVICE SYSTEM (3

2.1试验目的及内容P URPOSE AND C ONTENT (3 2.2试验条件P RE-CONDITIONS (3 2.3试验步骤T EST S TEPS (4

2.3.1 厂用电、自用电0.415KV无水调试Dry commissioning of 0.415KV station service and

auxiliary power supply (4

2.3.2 柴油发电机组调试Commissioning of diesel generator (5

3直流系统无水调试方案DRY COMMISSIONING PROCEDURE OF DC SYSTEM (7

3.1试验目的及内容P URPOSE AND C ONTENT (7 3.2试验条件P RE-CONDITIONS (7 3.3试验步骤T EST S TEPS (7

411KV厂用电系统无水调试DRY COMMISSIONING OF 11KV STATION SERVICE (9

4.1试验目的及内容P URPOSE AND C ONTENT (9 4.2试验条件P RE-CONDITIONS (9 4.3试验步骤T EST S TEPS (9

5压缩空气系统无水调试DRY COMMISSIONING OF COMPRESSED AIR SYSTEM (12

5.1试验目的及内容P URPOSE AND C ONTENT (12 5.2试验条件P RE-CONDITIONS (12 5.3试验步骤T EST S TEPS (12 5.4试验记录表T EST FORM (15 6透平油及绝缘油系统调试 (16

6.1试验目的及内容T EST PURPOSE AND CONTENT (16

6.2试验条件T EST CONDITION (16 6.3试验步骤T EST STEP (17

7检修、渗漏、技术供水系统无水调试 (19

DRY TEST OF MAINTENANCE, LEAKAGE, TECHNICAL WATER SUPPLY SYSTEM..................................................................................................................... 错误!未定义书签。

7.1试验目的及内容P URPOSE AND CONTENT OF TEST (19 7.2试验条件T EST CONDITION (19 7.3试验步骤T EST STEP (20

7.3.1 渗漏排水系统无水调试Dry test of leakage drainage system (20 7.3.2技术供水系统调试Technical water supply system commissioning (21 8调速器系统无水调试DRY COMMISSIONING OF GOVERNING SYSTEM.. 25 8.1试验目的及内容P URPOSE AND C ONTENT (25

8.2试验条件P RE-CONDITIONS (25 8.3试验步骤T EST S TEPS (26

8.3.1电气控制部分检查Inspection of electrical controlling section (26 8.3.2 液压部分调试Commissioning of hydraulic section (27 8.3.3 调速器调试Commissioning of governor (29

8.3.4 与监控联合调试Joint commissioning with monitoring and controlling (32 9机组辅助系统无水调试 (67