计算实例:(作业) 答案:
编号__________________ 日期Date______________
单位名称
Messr____________
船名 装/卸货种及吨数
Loading/Discharging__20,000__metric tons of_Grain in Bulk _
M.V.___Brodie_
时间 Time
日期 Date
星期 Day
递交装卸准备就绪通知书时间
Notice of Readiness Tendered: 1100 Hrs Wednesday 9th June
接受装卸准备就绪通知书时间
Notice of Readiness Accepted:
装卸时间起算时间
Laytime Commenced to Count: 1300 Hrs Wednesday 9th June
开始装卸时间
Loading/Discharging Commenced: 0700 Hrs Thursday 10th June
装/卸货完毕时间
Loading/Discharging Completed: 1200 Hrs Tuesday 15th June
节省/滞期时日期 星期 时间Hours 说明 可用时间 Laytime 实用时间 间 Time saved/lost D H M 0 0 0 Date Day of the Week Wednesday Wednesday Wednesday From O600 1100 1300 to Description Laytime allowed used D D H M H M 0 0 9th June Arrived 0 0 0 9th June Laytime commence 9th June 0 9th June
Wednesday
1300 O000 O000 1700 O000 2400 2400 1700 2400 O700 Laytime count Laytime count LOADING not to count not to count 11 24 17 0 0 11 24 17 0 0 0 0 0 0 0 10th June Thursday
Friday Friday Saturday 11th June
11th June
12th June
Saturday O700 1600 Saturday 1600 2400 Sunday O000 2400 Monday O000 O700 Monday O700 O900 Monday O900 1000 Monday 1000 2400 Tuesday
O000 1200
Tuesday 1200
1900
速遣/滞期费率 Rate of Despatch/Demurrage:
速遣/滞期费总金额
overtime work 9 9 0 not to count 0 0 0 not to count 0 0 0 not to count 0 0 0 Actual LOADING
2 2 0 rain 0 0 0 LOADING 14 14 0 LOADING Complete 12 12 0 Allowed time used up
7 0 7 合计 96 Hours 89 hours 7 Total
Despatch: 2500×7/24=729 USD
For and behalf of the Shippers
As Agents
12th June
12th June
13th June
14th June
14th June
14th June
14th June
15th June
15th June
Total Amount of Despatch/Demurrage: