租船实务装卸时间计算案例 下载本文

内容发布更新时间 : 2024/5/12 22:56:39星期一 下面是文章的全部内容请认真阅读。

计算实例:(作业) 答案:

编号__________________ 日期Date______________

单位名称

Messr____________

船名 装/卸货种及吨数

Loading/Discharging__20,000__metric tons of_Grain in Bulk _

M.V.___Brodie_

时间 Time

日期 Date

星期 Day

递交装卸准备就绪通知书时间

Notice of Readiness Tendered: 1100 Hrs Wednesday 9th June

接受装卸准备就绪通知书时间

Notice of Readiness Accepted:

装卸时间起算时间

Laytime Commenced to Count: 1300 Hrs Wednesday 9th June

开始装卸时间

Loading/Discharging Commenced: 0700 Hrs Thursday 10th June

装/卸货完毕时间

Loading/Discharging Completed: 1200 Hrs Tuesday 15th June

节省/滞期时日期 星期 时间Hours 说明 可用时间 Laytime 实用时间 间 Time saved/lost D H M 0 0 0 Date Day of the Week Wednesday Wednesday Wednesday From O600 1100 1300 to Description Laytime allowed used D D H M H M 0 0 9th June Arrived 0 0 0 9th June Laytime commence 9th June 0 9th June

Wednesday

1300 O000 O000 1700 O000 2400 2400 1700 2400 O700 Laytime count Laytime count LOADING not to count not to count 11 24 17 0 0 11 24 17 0 0 0 0 0 0 0 10th June Thursday

Friday Friday Saturday 11th June

11th June

12th June

Saturday O700 1600 Saturday 1600 2400 Sunday O000 2400 Monday O000 O700 Monday O700 O900 Monday O900 1000 Monday 1000 2400 Tuesday

O000 1200

Tuesday 1200

1900

速遣/滞期费率 Rate of Despatch/Demurrage:

速遣/滞期费总金额

overtime work 9 9 0 not to count 0 0 0 not to count 0 0 0 not to count 0 0 0 Actual LOADING

2 2 0 rain 0 0 0 LOADING 14 14 0 LOADING Complete 12 12 0 Allowed time used up

7 0 7 合计 96 Hours 89 hours 7 Total

Despatch: 2500×7/24=729 USD

For and behalf of the Shippers

As Agents

12th June

12th June

13th June

14th June

14th June

14th June

14th June

15th June

15th June

Total Amount of Despatch/Demurrage: