Velocity and Veracity. ( )refers to the quantity of generated and stored data.
A. Volume B.Variéty – C.Velocity D. Veracity
【参考答案】A 【答案解析】
? 72.( ) is the extemsion of internet connectivity into physical devices and
everyday objects.Fmbedded with electronics, internet connectivity, and other forms of hardware (such as sensors),these devices can communicate and interact with others over the Internet. and they can beremotely monitored and controlled.
A.Cloud Computing B.Internet of Things C.Block Chain
D.Artificial Intelligence
【参考答案】B
【答案解析】.()是将互联网连接扩展到物理设备和日常物品中。这些设备与电子设备、
互联网连接和其他形式的硬件(如传感器)结合在一起,可以通过互联网与其他设备进行通信和交互。它们可以被远程监控和控制。
? 73.( ) is a process of developing a document that formally authorizes the
existence of a projectand provides the project manager with the authority to apply organizational resources to projectactivities.
A.Develop Project Charter B.Manage Project Knowledge
C.Monitor and Control Project Work D.Close Project
【参考答案】A
【答案解析】()是一个开发正式授权项目存在的文件的过程,并为项目经理提供将组织
资源应用于项目活动的权限。
? 74.( ) is a process of developing a detailed description of the project and product.
A.collect requirements
2019年上半年上午-系统集成项目管理工程师-上午试题及答案与解析(软考真题-基础知识)21/22
全国计算机技术与软件专业技术资格(水平)考试库
china_nejcer
B.Definition scope C.validate scope D.control range
【参考答案】B
【答案解析】()是对项目和产品进行详细描述的过程。
? 75.( ) is a process of monitoring the status of the project to update the
project costs and managechanges in the cost baseline.
A.Plan Cost Management B. Estimatet Costs C.Determine Budget D.Control costs
【参考答案】D
【答案解析】()是一个监控项目状态的过程,用于更新项目成本并管理成本基准中的更
改。