作 业 指 导 书 编 号:土—05—01—5 工程名称: 华电六安发电厂(2×135MW)工程 作业项目名称:烟囱内衬施工 编制单位:安徽电建一公司六安电厂项目部建筑科 批 准:叶雄师 安全科:刘 虎 质 量:钱成斌 工程部:朱家直 审 核:王林伟 编 制:王道家 出版日期

时间: 时间:2004.9.18 时间:2004.9.14 时间:2004.9.14 时间:2004.9.12 时间:2004.9.7 版 次 目录

1.作业任务 ·················································································································· 1 1.1工程概况 ················································································································ 1 1.2 施工范围 ··············································································································· 1 1.3 工程量 ·················································································································· 1 1.4 工期要求 ··············································································································· 1 2.编写依据 ·················································································································· 1 3.作业准备和条件 ········································································································ 1 3.1 人员配备 ··············································································································· 1 3.2 工器具配备 ··········································································································· 2 3.3 设备、材料要求 ···································································································· 2 3.4 对上道工序的要求 ································································································· 2 4.作业方法与工艺要求 ································································································· 2 4.1 作业主体方案·········································································································· 2 4.2、作业方法与步骤 ··································································································· 3 5.作业质量标准及检验要求 ·························································································· 4 5.1 作业质量标准·········································································································· 4 5.2 检验要求 ················································································································ 5 6.职业安全健康、环境管理和文明施工 ········································································· 5 7.附录 ························································································································· 6

华电六安发电厂(2*135MW)工程烟囱内衬施工作业指导书 1

1.作业任务 1.1工程概况

华电六安发电厂(2×135MW)工程设钢筋混凝土烟囱一座,烟囱全高180m,烟囱顶部外直径5.80m。在灰斗平台以上设计有内衬,内衬砌体为耐酸胶泥砌筑陶土耐酸砖,30m以下内衬厚度为240mm,30m~180m内衬厚度为120mm。保温隔热材料为憎水珍珠岩板,厚度为100mm。烟囱钢筋砼筒壁内表面需涂刷GFVC-2厚浆型防腐涂料。

1.2 施工范围

烟囱内壁耐酸涂料涂刷、烟囱隔热层及内衬砌筑。

1.3 工程量

项目名称 内衬砌筑 隔热层 防腐涂料涂刷 工程量 725m 492m 5031m 2331.4 工期要求

与筒壁工程同步进行。

2.编写依据

2.1 烟囱筒身施工图(34-F0901S-T0302) 2.2 建筑施工手册(中国建筑工业出版社第三版) 2.3 火电施工质量检验及评定标准(土建工程篇) 2.4 烟囱施工及验收规范(GBJ78-85)

3.作业准备和条件 3.1 人员配备

职务或工种 技术员 施工员 安环员 材料员 人数 1 1 1 1 职务或工种 瓦工 木工 操作工 电工 人数 10 3 3 2