内容发布更新时间 : 2024/12/27 22:47:57星期一 下面是文章的全部内容请认真阅读。
蒙城县2014年“两区”二期道排项目施工 现浇箱涵工程模板与支架专项施工方案
编制人: 审核人: 审批人:
编制单位:山西建筑工程(集团)总公司蒙城2014年“两区”二期道排
项目施工项目部
编制时间:二零一四年十月三十一
目 录
一、工程概况············································································································3
二、施工组织和管理机构························································································3
三、箱涵涵身施工工艺流程····················································································4
四、施工进度计划····································································································5
五、箱涵涵身施工要点····························································································5
六、扣件钢管顶板模板支架计算············································································6
七、腹板(墙)模板计算························································································7
八、施工技术要求····································································································7
九、安全管理···········································································································12
十、确保工程质量的措施·······················································································15
十一、文明施工·······································································································16
十二、预防伤害安全生产事故应急救援预案························································17
十三、附件················································································································23
附件1·························································································································23
附件2·························································································································29
附件3·························································································································35
- 2 -
一、工程概况
蒙城县2104年“两区”二期道排项目施工工程共有箱涵一座,为纬一路马沟涵,本箱涵为4.0X2.5m的三孔箱涵,中心桩号为K0+610,箱涵中心线为道路中心线交角为86.136°,涵长13.95m,采用整体式钢筋混凝土涵身,扶壁式挡土墙翼墙,单箱涵净宽4.0米,净高2.5米,顶板厚度34cm,腹板厚3.2m,涵身混凝土为C30现浇混凝土,涵洞及挡墙基础下铺设10cm厚素C20混凝土垫层。
二、施工组织和管理机构
项目经理:张德良 质检员: 项鹏
项目技术负责人:李晓刚
施工员:童大柱施工员:许滨材料员:李世礼
安全员:樊斌资料员:吴倩质检工程师:项鹏
钢筋班组 模板班组 混凝土班组 其他综合班组 - 3 -
三、箱涵涵身施工工艺流程
测量放样 碎石垫层施工 钢筋检验 浇注垫层砼 钢筋制作 绑扎底板34cm及腹板32cm钢筋 安装模板 浇注底板34cm及腹板32cm砼养护 模板拆除 搭设顶板支架和模板 绑扎腹板及顶板钢筋 安装腹板模板 浇筑顶板和腹板砼 砼养护 拆除模板和支架
- 4 -
四、施工进度计划
见附件3。
五、箱涵涵身施工要点
1、编制依据
①施工图设计文件及地勘报告。
②国家有关的政策、法规、施工验收规范和工程建设标准强制性条文(城市建设部分),以及现行有关施工技术规范、标准等。
③《公路桥涵设计规范》; ④《公路桥涵施工技术规范》; ⑤《公路桥涵施工手册》;
⑥《建筑施工模板安全技术规范》JGJ162-2008; 2、测量放样
箱涵测量放样时,应注意核对箱涵纵横轴线的地形剖面图是否与设计图相符,应注意箱涵长度、箱涵标高的正确性。对斜交箱涵、曲线上和陡坡上箱涵,应考虑交角、加宽、超高和纵坡对箱涵具体位置、尺寸的影响,并注意锥坡、翼墙、一字墙和箱涵墙身顶部和上下游调治构造物的位置、方向、长度、高度、坡度,使之符合技术要求。
3、C20砼垫层
10cm的砼垫层砼采用商品砼,商品砼采用搅拌车运至现场模浇注,振捣密实,采用覆盖土工布浇水保湿养护;
5、箱涵涵身施工
箱涵涵身竖向施工施工分2个阶段,第一阶段浇筑至底板内壁以上30cm;第二阶段浇筑剩余部分,2次浇筑的接缝应保证有良好的衔接面(粗糙、干净并不得有堆落的混凝土和砂浆)。
(1)模板安装前,应由测量放出承台和腹板的边线和中轴线,并用墨斗弹出边、轴墨线,放样后经监理检查,合格后安装模板;
(2)箱涵顶板底模、腹板侧模采用12mm、15mm厚木胶合板做面板,箱涵腹板模板支撑体系内楞采用5cm×10cm方木,间距20cm、外楞采用Φ48×3.0mm及Φ14对拉螺栓,间距40
- 5 -