the project manager that some key stakeholders were forgotten during a previous similar project. The project sponsor mandates that the project manager ensure that all stakeholders be identified
What approach should the project manager take to gather the required information A. Consult the lessons learned from the previous project B. Consult the project charter from the previous project C. Start to prepare a stakeholder analysis from scratch
D. Obtain the project management plan from the previous project
53. 项目经理被任命管理一个新项目。项目发起人已经起草完项目章程的第一稿。项目发起
人通知项目经理在之前一个类似项目中某些关键干系人被遗漏了。项目发起人要求项目经理确保所有项目干系人均已识别。
若要收集必要信息,项目经理应该采取什么方式? A. 查询之前项目的经验教训 B. 查询之前项目的项目章程 C. 开始从头准备一份干系人分析 D. 获得之前项目的项目管理计划
54.After confirming the availability of human resource and obtaining teams for project assignments, the project manager discovers that the resources will not sufficiently meet the project schedule. The project manager meets with a functional manager who agrees to make additional resources available for the duration of the project
What tool or technique does the project manager use? A. Negotiation B. Acquisition C. Pre-assignment D. Co-location
54. 确认人力资源可用性并获得执行项目任务的团队后,项目经理发现资源不足以满足项目
进度计划,项目经理与职能经理开会,职能经理同意为项目工期增加可用资源。 项目经理是用的是什么工具或技术 A. 谈判 B. 招募 C. 预分派 D. 集中办公
55.As a result of financial issues, seller a will be late in delivering a critical product. According to the contingency plan, seller B is an approved vendor and could deliver a similar product
What should the project manager do next?
A. Submit a change request to the change control board B. Hold a bidder meeting with potential sellers
C. Review business case to ensure the return on