内容发布更新时间 : 2025/7/4 5:03:13星期一 下面是文章的全部内容请认真阅读。
D. Establish a benchmark
64. 完成定义范围过程后,项目经理应使用哪项技术来生成可靠估算并管理成本和活动持续
时间? A. 分解
B. 紧前关键绘图法 C. 挣值管理 D. 确立基准
65.At a project status meeting, the vendor reports that they will miss the deadline to release software, which will be required for the project to move forward. What should the project manager do first? A. Update the project management plan
B. Negotiate a new release date with the vendor C. Perform the change control process D. Issue a change request for approval
65. 在状态会上,供应商报告他们将会延误软件发布期限,而发布软件是项目继续推进的一
个必要条件。
项目经理首先应该做什么? A. 更新项目管理计划
B. 与供应商协商一个新的发布日期 C. 执行变更控制过程 D. 签发变更请求获得批准
66.A web development firm delivers a product to the client on time and 20% over the original budget. The client is currently soliciting bids for a new web project. What should the web development firm’s project manager do during the closure phase to enhance customer relations?
A. Request requirements for the new web project B. Conduct a stakeholder analysis
C. Meet with the client to review lessons learned
D. Implement corrective actions of the budget controlling
66. 一家网络开发公司按时向客户交付产品,但超出原始预算20%。客户目前正在为一个新
网络项目投标。若要增强客户关系,网络开发公司的项目经理在收尾阶段应怎么做? A. 索取新网络项目的需求 B. 进行干系人分析
C. 与客户开会,审查经验教训 D. 执行预算控制的纠正措施
67.Theproject manager begins to close a supplier contract. In order to ensure the correct acceptance of the contract, which of the following completing sequence should the project manager follow?
A. Verify completed work, close financial work, close contract B. Close contract, verify completed work, close financial work C. Close financial work, close contact, verify completed work
D. Verify completed work, clos